Contractors working on Cadent’s gas mains replacement scheme have hit their annual target with weeks to spare. Engineering firm Costain announced that it has already met its target to replace 340km of gas mains in Cadent’s East of England network by the end of March. The contractor is now expecting to have replaced 380km of gas mains by the end up the year, some 40km more than its target.