News
Latest
Connections queue blocked by 62GW of ‘phantom’ projects
The connections queue for the transmission network contains around 62GW of "phantom" projects that are due to be connected by 2029 but still remain in the scoping phase and may not have secured land rights or applied for planning permission. Centrica said these projects account for roughly a fifth of the 371GW of projects in the Transmission Entry Capacity register and more than a half of the 114GW worth of projects due to be connected before 2029.
1 year ago
IEA: Golden age of gas is nearing an end
1 year ago
Ofgem to claw back £24m from Shell Energy
1 year ago
Utility Week Awards 2023 shortlist revealed
1 year ago
UU adds HGVs to electric fleet
1 year ago
Water bills deemed unfair, yet affordable
1 year ago
Scottish Power granted PPM warrants
1 year ago
Load More