Wessex Water first looked at nature-based solutions for P treatment at its Cromhall WRC after water quality modelling showed that a 2.0mgP/l total P permit would be necessary at the site to meet water quality targets. This would require significant investment in tertiary treatment such as ferric dosing.
Rather than opt for the traditional energy and chemical-intensive solution, Wessex decided to trail an integrated constructed wetland as a more sustainable approach to reduce nutrient discharges – the first time a wetland had been used for this purpose in the UK.
Wessex had been in discussions with local landowner the Tortworth Estate and the Environment Agency (EA) since 2010, but without a driver for the project in the Water Industry National Environment Programme (WINEP) for PR14 the project had to wait until PR19 to go ahead.
Operational from April 2020, the wetland is 0.8ha in area and is arranged in a modular design with a total of 12 cells combining open water, surface flow march and wet grassland habitat types.
“Our experimental site at Cromhall was very much the first wetland in this country for P removal. We worked with the Wildfowl and Wetlands Trust consultancy to design it, but I think it is probably fair to say that we weren’t sure what the design should be given the limited data sets available.
“There were no templates for this, no one had done this before, so we used our combined experience and knowledge to design a wetland that we thought would probably hit a 2.0mgP/l concentration,” says Ruth Barden, director of environmental solutions at Wessex Water.
Intensive monitoring at the site until November 2021 revealed the wetland was achieving a 27.5% reduction in total P and meeting its proposed 2.0mgP/l permit limit, but the company is not entirely satisfied with the results.
“It broadly does achieve a 2mg/l discharge concentration on an annual basis, but not quite. Its providing about 20% P reduction, but we are not convinced that is P removal. We think its just being held up in the wetland temporarily and then might get re-released at another stage,” says Barden.
“One of the findings from Cromhall design is that wetlands are probably not all we had hoped they would be in terms of P.”
Wessex has identified some design issues with the wetland, such as the cells being too deep and some preferential flow, which is limiting the retention time within the wetland needed to enable maximum P uptake by the plants.
“If we reconfigured it and did some more work, which we are inclined to do, we think we could get a greater level of P removal but even so I don’t think its quite going to hit the level of the really stringent targets which are now needed.”
The Levelling-up and Regeneration Bill which was passed at the end of October has effectively ruled out P wetlands as being an option across the nearly half of Wessex’s operational area due to nutrient neutrality.
This legislation requires all sewage treatment works in areas above 2,000 population equivalent to achieve P removal down to the technically achievable limit, which Barden says is not possible using a P wetland due to the amount of land that would be required. And without the P driver, it will be difficult to make the case for the wetlands, she adds.
“The business case doesn’t really stack up as well as it could have done. They take up a huge amount of land and if the wider benefits – such as nitrogen, emerging contaminant, pathogen removal or biodiversity gain – that they are delivering are not truly valued then it’s difficult to make that case.”
The biodiversity natural capital gain of the wetlands was measured as being 111% for increased habitat, and 42% in increased hedgerow biodiversity units compared to the arable land before construction.
“At the moment the focus is very much on hitting a P target from an asset, it’s not about the wider benefits that asset might generate, or even the disbenefits that it might deliver in terms of increased carbon, be that embedded or operational carbon from a grey asset that can hit that P standard. That’s just not really taken into account – it is by companies but not by the regulator.”
The company has submitted new proposals to the department for environment, food and rural affairs for tackling nutrients, which sees its business plan proposals for P wetlands cut down to just two new schemes.
“In our proposal we are looking at delivering two wetlands for P removal whereas previously we were thinking of tens of wetlands. They are at very small sites, with between 100-150 population equivalent and where the modelled permits would only need to be 3.0mgP/l, and that’s it, which is disappointing, but that’s where we are,” says Barden.
Please login or Register to leave a comment.